The front of the building - steel pillars now all in place |
Brick cladding going up - front of building |
Reception with general office on right and meeting room, PA's office and Principal's office on left |
Ducting in DT |
Principal's office |
Dining Room |
Covered area - Students' Courtyard |
Stairs to first floor |
The hall - will house 3D projector and cinema seating for 260 |
The seating will, at the touch of a button, retract |
The lift shaft |
ICT |
Windows |
The building is split level, so this crane is actually on the first floor |
The huge window in one of the stairwells |
Science |
The link between the main building and the Sports Hall |
The Sports Hall is now sealed |
Ground: MFL/Music, First: English, Second: Humanities |
ICT |
Looking out to 3G pitch. The wall is the start of the changing rooms. |
Science corridor |
The view from one of the Science rooms |
The window to the balcony |
The Science/Art balcony |
The far end of the Sports Hall |
The Sports Hall is nearly joined to the main building |
The DT/Maths/Science wing |
DT/Maths/Science |
Windows going in and brick going up - front of building |
The Art/Science balcony above Reception |
Brickwork starts on the side of the Hall |