Ignore the wheelie bin. Look at the brick work: will be 'topped out' soon. |
![]() |
The 'community' rooms - classroom which can be accessed without entering the building. |
![]() |
Furniture has started to arrive - DT. |
![]() |
DT furniture. |
![]() |
DT furniture. |
![]() |
Plastering and painting has started. This wall will house the interactive surface. |
![]() |
More trays going in for cabling. |
![]() |
More and more services now added. |
![]() |
VP's office. |
![]() |
DT. |
![]() |
Plumbing in toilet areas has started... |
![]() |
These are as clean as they'll ever be... |
![]() |
The lift has arrived. |
![]() |
The lift. |
![]() |
The hall. |
![]() |
Large areas - such as the ICT area on the first floor - are being used for storage. |
![]() |
ICT. |
![]() |
The switches have gone in. |
![]() |
Huge cables. |
![]() |
More cables. |
![]() |
It's a bit like looking inside a plug... |
![]() |
The switch cabinet. |
![]() |
The boiler room. The boilers are arriving soon. |
![]() |
Boiler room. |
![]() |
Pellets will be fed in here. |
![]() |
The Outdoor Education store. |
![]() |
Outdoor Education store. |